Lidl GmbH acquired the site of an old power station in Northfleet Kent .

The initial phase of works was to provide a safe environment for the main building phase.

High Peak Geotechnical Ltd have undertaken many projects in the area and working together with consultants RSK Ltd & Graham Daws Associates the cliff was stabilised over the winter of 2012.

The works included, Vegetation Clearance, & installation of 21000m2 of Rock Netting, 2000 GRP Rock Bolts & Erosion Control Matting supplied by Minova Weldgrip.